  • Smoke Testing Project – Final Update – July 6, 2025

    English and Spanish Versions are Provided Below – A continuación se proporcionan versiones en inglés y español.

    As part of our continued partnership with the Brunswick-Glynn Joint Water and Sewer Commission, McKim & Creed will begin fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.


    Como parte de nuestra colaboración continua con la Comisión Conjunta de Agua y Alcantarillado de Brunswick-Glynn, McKim & Creed comenzará los trabajos de campo para el Proyecto de Servicios de Pruebas con Humo y Tinte el lunes 27 de octubre de 2025.


    Distribution of smoke notices began on October 27th, 2025, and smoke testing was started October 28th, 2025. Because of Brantly County forest fires in southwestern Georgia, all field work was temporarily suspended in early May 2026. After the suspension was lifted, field work was completed on May 18th, 2026. Within the basins selected for inspection, 1,069,148 feet of mainline smoke was tested. A total of 1123 defects were located during the smoke testing, and these are summarized below by defect type and area.

    Each smoke defect was reviewed, and a repair recommendation was created. These recommendations were assigned a priority ranking of 1 to 3 based on the following criteria:

    • Priority 1 defects are recommended to be repaired first, and these are typically located in
      locations subject to larger amounts of runoff such as depressions, ditches, area drains or
      stormwater structures.
    • Priority 2 repair recommendations generally include manhole covers in streets, cleanout
      defects in yards, and similar inflow sources.
    • Priority 3 is assigned to smoke defects that are likely to contribute the least amount of
      inflow but still should be considered for repair. These defects may be above grade and
      not subject to runoff during a typical rain event but could still contribute extraneous flows
      through direct rainfall or during extreme events that may cause flooding around the
      defect.

    Please visit our Annual Goals Page to stay informed on the progress of each defect repair.

  • Smoke Testing Project – Weekly Update – February 2, 2026

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    Smoke testing was successfully completed during the week of January 26, 2026. Beginning the week of February 2, McKim & Creed will start dye testing.


    McKim & Creed comenzó los trabajos de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025.

    Las pruebas de humo se completaron con éxito durante la semana del 26 de enero de 2026. A partir de la semana del 2 de febrero, McKim & Creed iniciará las pruebas con tinte.

  • Smoke Testing Project – Weekly Update – January 26, 2026

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    During the week of January 26, 2026, our crews will be working on Saint Simons Island in the Redfern Village area as well as the East Beach area on Ocean Boulevard. Due to Monday’s weather, no smoke testing will be taking place today. Please review the maps for the scheduled testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025.

    Durante la semana del 26 de enero de 2026, nuestras cuadrillas estarán trabajando en Saint Simons Island, en el área de Redfern Village así como en el área de East Beach sobre Ocean Boulevard. Debido al clima del lunes, no se realizará ninguna prueba de humo hoy. Por favor, revise los mapas para conocer las ubicaciones programadas de las pruebas.

    Overview

    Anticipated Smoke Testing Area_01_26_2026

    Anticipated Smoke Testing Area_01_27_2026

    Anticipated Smoke Testing Area_01_28_2026

    Anticipated Smoke Testing Area_01_29_2026

    Anticipated Smoke Testing Area_01_30_2026Area1

    Anticipated Smoke Testing Area_01_30_2026Area2

  • Smoke Testing Project – Weekly Update – January 19, 2026

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    During the week of January 19, 2026, our crews will be working on Saint Simons Island in the Kings Way and Mallery Street areas. Please review the maps for the scheduled testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025.

    Durante la semana del 19 de enero de 2026, nuestros equipos estarán trabajando en Saint Simons Island, en las áreas de Kings Way y Mallery Street. Por favor, revise los mapas para conocer las ubicaciones programadas para las pruebas.

    WeekBeginning20260119Overview

    Anticipated Smoke Testing Area_01_19_2026

    Anticipated Smoke Testing Area_01_20_2026

    Anticipated Smoke Testing Area_01_21_2026

    Anticipated Smoke Testing Area_01_22_2026

    Anticipated Smoke Testing Area_01_23_2026

     

  • Smoke Testing Project – Weekly Update – January 12, 2026

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    During the upcoming week (1/12/26), our crews will be working on Saint Simons Island in the Demere Road and Frederica areas. Please review the maps for the scheduled testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025.

    Durante la próxima semana (1/12/26), nuestras cuadrillas estarán trabajando en la Isla de Saint Simons, en las áreas de Demere Road y Frederica. Por favor, revise los mapas para conocer las ubicaciones programadas de las pruebas.

    20260112WeekofOverview

    Anticipated Smoke Testing Area_01_12_2026

    Anticipated Smoke Testing Area_01_13_2026

    Anticipated Smoke Testing Area_01_14_2026

    Anticipated Smoke Testing Area_01_15_2026

    Anticipated Smoke Testing Area_01_16_2026

  • Smoke Testing Project – Weekly Update – January 5, 2026

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    This week (1/5/26), our crews will be working in the Chapel Crossing FLETC area. Please review the maps for upcoming testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025.

    Esta semana (5/1/26), nuestros equipos estarán trabajando en el área de Chapel Crossing FLETC. Por favor, revise los mapas para conocer las próximas ubicaciones de prueba.

    Anticipated Smoke Testing Area_01_07_2026

    Anticipated Smoke Testing Area_01_09_2026

    20260105WeekofOverview

  • Smoke Testing Project – Weekly Update – December 15, 2025

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025.

    This week (12/15/25), our crews will be working in the Downtown Brunswick area. Please review the maps for upcoming testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes, 27 de octubre de 2025.

    Esta semana (15/12/25), nuestras cuadrillas estarán trabajando en el área del Centro de Brunswick. Por favor, revise los mapas para ver las próximas ubicaciones de las pruebas.


    Anticipated Smoke Testing Area_12_15_2025

    Anticipated Smoke Testing Area_12_16_2025

    Anticipated Smoke Testing Area_12_17_2025

    Anticipated Smoke Testing Area_12_18_2025

    Weekof20251215Overview

  • Smoke Testing Project – Weekly Update – December 1, 2025

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025. We hope everyone had a wonderful Thanksgiving holiday!

    This week (12/01/25), our crews will be working in the Chapel Crossing area. Please review the maps for upcoming testing locations.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025. ¡Esperamos que todos hayan disfrutado de un maravilloso Día de Acción de Gracias!

    Esta semana (01/12/25), nuestras cuadrillas estarán trabajando en el área de Chapel Crossing. Por favor, revisen los mapas para ver las próximas zonas de prueba.


    20251201WeekOverview

    Anticipated Smoke Testing Area_12_3_2025

    Anticipated Smoke Testing Area_12_4_2025

    Anticipated Smoke Testing Area_12_5_2025

  • Smoke Testing Project – Weekly Update – November 17, 2025

    English and Spanish Versions are Provided Below – A continuación se proporcionan versiones en inglés y español.

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025, and we are now entering our fourth week. For this week (11/17/25), please note that our team will pause smoke testing for the next two weeks. A crew member will be on-site next week collecting data, but no active smoke testing will take place. In addition, testing will be fully suspended during the week of 11/24 in observance of Thanksgiving. We will resume smoke testing the week of 12/1, and a notice with the updated schedule will be shared in advance to keep everyone informed.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025, y ahora estamos entrando en nuestra cuarta semana. Para esta semana (11/17/25), tenga en cuenta que nuestro equipo hará una pausa en las pruebas de humo durante las próximas dos semanas. Un miembro del equipo estará en el sitio la próxima semana recopilando datos, pero no se realizarán pruebas de humo. Además, no habrá pruebas durante la semana del 11/24 en observancia del Día de Acción de Gracias. Reanudaremos las pruebas de humo la semana del 12/1, y enviaremos un aviso con el calendario actualizado con anticipación para mantener a todos informados.

  • Smoke Testing Project – Weekly Update – November 10, 2025

    English and Spanish Versions are Provided Below – A continuación se proporcionan versiones en inglés y español.

    McKim & Creed began fieldwork for the Smoke and Dye Testing Services Project on Monday, October 27, 2025. We’re now entering our third week of testing, and crews will be working in several neighborhoods throughout the area. To see when testing will take place near you, please check the mapped locations for this week.


    McKim & Creed comenzó el trabajo de campo para el Proyecto de Servicios de Pruebas de Humo y Tinte el lunes 27 de octubre de 2025. Ahora estamos entrando en nuestra tercera semana de pruebas, y los equipos estarán trabajando en varios vecindarios de la zona. Para ver cuándo se realizarán las pruebas cerca de usted, por favor consulte los mapas de las ubicaciones para esta semana.

    WeekOverview

    Anticipated Smoke Testing Area_11_10_2025_1

    Anticipated Smoke Testing Area_11_10_2025_2

    Anticipated Smoke Testing Area_11_10_2025_3

    Anticipated Smoke Testing Area_11_11_2025_1

    Anticipated Smoke Testing Area_11_11_2025_2

    Anticipated Smoke Testing Area_11_11_2025_3

    Anticipated Smoke Testing Area_11_12_2025_1

    Anticipated Smoke Testing Area_11_12_2025_2

    Anticipated Smoke Testing Area_11_13_2025

    Anticipated Smoke Testing Area_11_14_2025