District and General Location: PS 2033 on 2913 Lawrence Road, Saint Simons Island PS 2034 on 130 Rice Mill Road, Saint Simons Island
Total Budget: $1.4M
Anticipated Construction Completion Date: TBD
Details: The project consists of the rehabilitation of Pump Station 2033 and 2034 due to the existing condition North end of Saint Simons Island.
Purpose: The purpose of the project is to ensure continuous delivery of wastewater to the Dunbar Treatment Plant. Improvements include replacing pumps, equipment, electrical, and control systems.