Project Info – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 3 Water Loops

  • Project Number: 2216S – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 3 Water Loops
  • District and General Location: South Mainland District – At the entrance of Planting Hammock Subdivision and adjacent to 186 Cinder Hill Drive in Brunswick, Georgia
  • Total Budget: $418,000
  • Anticipated Construction Completion Date: February 2026
  • Details: The project consists of water loop installations along Planting Hammock and between Cinder Hill Drive and Bartram Trail via open-cut and trenchless methods.
  • Purpose: To eliminate dead ends where water can become stagnant due to lack of use, improve water quality, and provide fire protection for JWSC customers.
  • Have More Questions? Please contact W. Todd Kline, P.E., Director of Engineering – tkline@bgjwsc.org

 

Visual Summary:

 

Monthly Active Construction Project Photo Report(s):

2025 June SPLOST Exit 29 Division 3 Water Loops

2025 July SPLOST Exit 29 Division 3 Water Loops

2025 August SPLOST Exit 29 Division 3 Water Loops

2025 September SPLOST Exit 29 Division 3 Water Loops

2025 October SPLOST Exit 29 Division 3 Water Loops

2025 November SPLOST Exit 29 Division 3 Water Loops

2025 December SPLOST Exit 29 Division 3 Water Loops

2026 January SPLOST Exit 29 Division 3 Water Loops

2026 February SPLOST Exit 29 Division 3 Water Loops

2026 March SPLOST Exit 29 Division 3 Water Loops

2026 May SPLOST Exit 29 Division 3 Water Loops

Project Info – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 2 500K Elevated Storage Tank

  • Project Number: 2216S – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 2 500K Elevated Storage Tank
  • District and General Location: South Mainland District – 503 South Port Parkway in Brunswick, Georgia.
  • Total Budget: $7.68M
  • Anticipated Construction Completion Date: February 2027
  • Details: Construction of the 500,000-gallon composite elevated storage tank.
  • Purpose: The installation of a new elevated storage tank, including electrical and SCADA system components, is planned to accommodate both current and future requirements of the neighboring community.
  • Have More Questions? Please contact W. Todd Kline, P.E., Director of Engineering – tkline@bgjwsc.org

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2025 June SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2025 July SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2025 August SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2025 October SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2025 November SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2025 December SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 January SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 February SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 March SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 May SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 June SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 July SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 August SPLOST Exit 29 Division 2 500K Elevated Storage Tank

2026 September SPLOST Exit 29 Division 2 500K Elevated Storage Tank

Project Info – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 1 Water Production Facility

  • Project Number: 2216S – SPLOST Exit 29 Water Production Facility and Elevated Storage Tank – Division 1 Water Production Facility
  • District and General Location: South Mainland District – 391 South Port Parkway in Brunswick, Georgia.
  • Total Budget: $4.64M
  • Anticipated Construction Completion Date: June 2026
  • Details: Construction of the well treatment improvements, pump control building,  and 200,000-gallon groundwater storage tank.
  • Purpose: Updating and improving the water production system to ensure it remains an efficient and reliable facility that meets the current and future demands of the surrounding community.
  • Have More Questions? Please contact W. Todd Kline, P.E., Director of Engineering – tkline@bgjwsc.org

 

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2025 June SPLOST Exit 29 Water Production Facility

2025 July SPLOST Exit 29 Water Production Facility

2025 August SPLOST Exit 29 Water Production Facility

2025 September SPLOST Exit 29 Water Production Facility

2025 October SPLOST Exit 29 Water Production Facility

2025 November SPLOST Exit 29 Water Production Facility

2025 December SPLOST Exit 29 Water Production Facility

2026 January SPLOST Exit 29 Water Production Facility

2026 February SPLOST Exit 29 Water Production Facility

2026 March SPLOST Exit 29 Water Production Facility

2026 May SPLOST Exit 29 Water Production Facility

2026 June SPLOST Exit 29 Water Production Facility

2026 July SPLOST Exit 29 Water Production Facility

2026 August SPLOST Exit 29 Water Production Facility

2026 September SPLOST Exit 29 Water Production Facility

Project Info – North Mainland Exit 42 Elevated Storage Tank

  • Project Number: 2213 – North Mainland Exit 42 Elevated Storage Tank
  • District and General Location: North Mainland District – 118 Cherokee Trail in Brunswick, Georgia.
  • Total Budget: $4.73M
  • Anticipated Construction Completion Date: TBD
  • Details: Construction of the 750,000-gallon composite elevated storage tank.
  • Purpose: The installation of a new elevated storage tank, including electrical and SCADA system components, is planned to accommodate both current and future requirements of the neighboring community.
  • Have More Questions? Please contact W. Todd Kline, P.E., Director of Engineering – tkline@bgjwsc.org

 

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2025 June Exit 42 EST

2025 July Exit 42 EST

2025 August Exit 42 EST

2025 September Exit 42 EST

2025 October Exit 42 EST

2025 November Exit 42 EST

2025 December Exit 42 EST

2026 January Exit 42 EST

2026 February Exit 42 EST

2026 March Exit 42 EST

2026 May Exit 42 EST

2026 June Exit 42 EST

2026 July Exit 42 EST

2026 August Exit 42 EST

2026 September Exit 42 EST

 

Project Info – Saint Simons Island – Dunbar Creek Water Pollution Control Facility

  • Project Number: #2106
  • District and General Location: Dunbar Creek Water Pollution Control Plant on 602 Palmetto Street.
  • Total Budget: $5.7M
  • Anticipated Construction Completion Date: TBD
  • Details: The project has a variety of system improvement projects related to the rehabilitation or replacement of unit processes and facilities at the plant to ensure continuous and reliable operations.
  • Purpose: The purpose of the project is to more effectively treat current flows and treat the estimated future flows, ensure long-term functionality, and Federal and State permit compliance.
  • Have More Questions? Please contact Andrew Burroughs, P.E., Executive Director – aburroughs@bgjwsc.org

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2022_July_DUNBAR_CREEK_WPCF_REHAB

2022_August_DUNBAR_CREEK_WPCF_REHAB

2022_September_DUNBAR_CREEK_WPCF_REHAB

2022_October_DUNBAR_CREEK_WPCF_REHAB

2022_November_DUNBAR_CREEK_WPCF_REHAB

2022_December_DUNBAR_CREEK_WPCF_REHAB

2023_January_DUNBAR_CREEK_WPCF_REHAB

2023_February_DUNBAR_CREEK_WPCF_REHAB

2023_March_DUNBAR_CREEK_WPCF_REHAB

2023_April_DUNBAR_CREEK_WPCF_REHAB

2023_May_DUNBAR_CREEK_WPCF_REHAB

2023_June_DUNBAR_CREEK_WPCF_REHAB

2023_July_DUNBAR_CREEK_WPCF_REHAB

2023_August_DUNBAR_CREEK_WPCF_REHAB

2023_September_DUNBAR_CREEK_WPCF_REHAB

2023_October_DUNBAR_CREEK_WPCF_REHAB

2023_NOVEMBER_DUNBAR_CREEK_WPCF_REHAB

2023_DECEMBER_DUNBAR_CREEK_WPCF_REHAB (1)

2023_DECEMBER_DUNBAR_CREEK_WPCF_REHAB (2)

2024_January_DUNBAR_CREEK_WPCF_REHAB

2024_January_DUNBAR_CREEK_WPCF_REHAB(2)

2024_February_DUNBAR_CREEK_WPCF_REHAB

2024_February_DUNBAR_CREEK_WPCF_REHAB (2)

2024_APRIL_DUNBAR_CREEK_WPCF_REHAB

2024_APRIL_DUNBAR_CREEK_WPCF_REHAB (2)

2024_MAY_DUNBAR_CREEK_WPCF_REHAB

2024_MAY_DUNBAR_CREEK_WPCF_REHAB (2)

2024_JUNE_DUNBAR_CREEK_WPCF_REHAB

2024_JUNE_DUNBAR_CREEK_WPCF_REHAB (2)

2024_July_DUNBAR_CREEK_WPCF_REHAB

2024_JULY_DUNBAR_CREEK_WPCF_REHAB 2

2024_August_DUNBAR_CREEK_WPCF_REHAB

2024_August_DUNBAR_CREEK_WPCF_REHAB (2)

2024_August_DUNBAR_CREEK_WPCF_REHAB (3)

2024_September_DUNBAR_CREEK_WPCF_REHAB

2024_September_DUNBAR_CREEK_WPCF_REHAB (2)

2024_October_DUNBAR_CREEK_WPCF_REHAB

2024_November_DUNBAR_CREEK_WPCF_REHAB

2024_November_DUNBAR_CREEK_WPCF_REHAB (2)

2024_December_DUNBAR_CREEK_WPCF_REHAB

2025_January_DUNBAR_CREEK_WPCF_REHAB

2025_February_DUNBAR_CREEK_WPCF_REHAB

2025_March_DUNBAR_CREEK_WPCF_REHAB

2025_April_DUNBAR_CREEK_WPCF_REHAB

2025_May_DUNBAR_CREEK_WPCF_REHAB

2025_June_DUNBAR_CREEK_WPCF_REHAB

2025_July_DUNBAR_CREEK_WPCF_REHAB

2025_August_DUNBAR_CREEK_WPCF_REHAB

2025_September_DUNBAR_CREEK_WPCF_REHAB

2025_October_DUNBAR_CREEK_WPCF_REHAB

2025_November_DUNBAR_CREEK_WPCF_REHAB

2025_December_DUNBAR_CREEK_WPCF_REHAB

2026_January_DUNBAR_CREEK_WPCF_REHAB

2026_February_DUNBAR_CREEK_WPCF_REHAB

Project Info – JWSC Facilities Improvements

    • Project Number:
    • District and General Location: Various locations in North mainland, South Mainland, and Saint Simons Island District
    • Total Budget: $450k
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of Administration building site improvements, painting, HVAC, Academy, and Harrington Warehouse Improvements as a part of the JWSC maintenance and monitoring program.
    • Purpose: The purpose of the project is to maximize the life of the existing assets and to efficiently manage inventories while maintaining readily accessible spare parts.
    • Have More Questions? Please Contact Pamela Crosby, Director of Procurementpcrosby@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

Project Info – SSI – Wesley Oak Circle Watermain Improvements

    • Project Number:
    • District and General Location: Saint Simons Island District in the Westley Oak Neighborhood Subdivision
    • Total Budget: $450K
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of replacing the 2-inch galvanized watermain loop with 6-inch and 8-inch sections.
    • Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure versus the consequence of a failure to the service area (i.e., size of community impact). Those areas with the greatest need where repairs would have the greatest impact are where JWSC focuses the efforts.
    • Have More Questions? Please Contact Derrick Simmons, Water Distribution Superintendent
      dsimmons@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2024 APRIL WESLEY OAKS CIRCLE WATERMAIN IMPROVEMENTS

2024 MAY WESLEY OAKS CIRCLE WATERMAIN IMPROVEMENTS

2024 JUNE WESLEY OAKS CIRCLE WATERMAIN IMPROVEMENTS

2024 JULY WESLEY OAKS CIRCLE WATERMAIN IMPROVEMENTS

2024 August WESLEY OAKS CIRCLE WATERMAIN IMPROVEMENTS

Project Info – SSI – Ocean Boulevard Water Improvements

    • Project Number:
    • District and General Location: Saint Simons Island District along Ocean Boulevard
    • Total Budget: $1.75M
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of replacing the existing watermain from East Beach to the Village on Saint Simons Island.
    • Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure versus the consequence of a failure to the service area (i.e., size of community impact). Those areas with the greatest need where repairs would have the greatest impact are where JWSC focuses the efforts.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

Project Info – North Mainland WPCF Land Acquisition and Engineering

    • Project Number:
    • District and General Location: Located in the North Mainland District
    • Total Budget: $TBD
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of purchasing the property and plant engineering design to meet future infrastructure and system needs.
    • Purpose: The purpose of the project is to secure a future public wastewater treatment plant site to serve the North Mainland District residents on the public sewer system.
    • Have More Questions? Please Contact Andrew Burroughs, P.E., Executive Director by email here: aburroughs@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

Project Info – South Mainland – Pump Station 3114 Forcemain Reroute

    • Project Number:
    • District and General Location: South Mainland District along South Port Parkway to the South Port Wastewater Treatment Plant
    • Total Budget: $400k
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of separate forcemain and reroutes to the head of the plant.
    • Purpose: The purpose of the project will reduce maintenance calls and disruptions. The reroute will also be shorter in length than the current alignment, which will result in energy savings and wear on existing pump station equipment.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):