Project Info – Academy Creek Ras Replacement

    • Project Number:
    • District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
    • Total Budget: $1.5M
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of replacing existing return activated sludge (RAS) pumps, piping, and electrical with chopper-style pumps due to the existing equipment systems reaching the end of their service life and needing to be replaced.
    • Purpose: The purpose of the project is to replace aging equipment to maintain a high level of service and reliability at the wastewater treatment plant.
    • Have More Questions? Please Contact Andrew Burroughs, P.E., Executive Director by email here: aburroughs@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2024 September Academy Creek RAS project

2024 September Academy Creek RAS project (2)

2024 September Academy Creek RAS project (3)

2024 October Academy Creek RAS project

2024 October Academy Creek RAS project (2)

2024 November Academy Creek RAS project (2)

2024 November Academy Creek RAS project

2024 December Academy Creek RAS project (2)

2024 December Academy Creek RAS project

2025 January Academy Creek RAS project

2025 January Academy Creek RAS project (4)

2025 January Academy Creek RAS project (3)

2025 January Academy Creek RAS project (2)

2025 February Academy Creek RAS project

2025 March Academy Creek RAS project

2025 April Academy Creek RAS project

2025 May Academy Creek RAS project

2025 June Academy Creek RAS project

2025 July Academy Creek RAS project

2025 August Academy Creek RAS project

2025 September Academy Creek RAS project

2025 October Academy Creek RAS project

2025 November Academy Creek RAS project

2025 December Academy Creek RAS project

2026 January Academy Creek RAS project

2026 February Academy Creek RAS project

Project Info – Systemwide – GA Environmental Finance Authority Loan Debt Service

    • Project Number:
    • District and General Location: Systemwide upgrade for North Mainland, South Mainland, and Saint Simons Island District.
    • Total Budget: $1.21M
    • Anticipated Construction Completion Date: TBD
    • Details: GEFA’s water and sewer financing programs offer low-interest financing for drinking water, reservoirs and water supply, water quality, stormwater and solid waste infrastructure. The JWSC has secured GEFA’s Clean Water State Revolving Fund Loan.
    • Purpose: The purpose of the loan is to replace aging assets to maintain a high level of service and reliability at the water production and distribution of potable water and to provide for sewage collection, treatment and disposal at the wastewater treatment plants.
    • Have More Questions? Please Contact LaDonnah S. Roberts, Deputy Executive Director by email here: lroberts@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

Project Info – South Mainland – City of Brunswick – Pump Station 3101, 4001, and 4002 Upgrade

    • Project Number:
    • District and General Location: PS3101 on 293 South Port Parkway, South Mainland PS4001 on 301 3rd Avenue, the City of Brunswick PS4002 on 1309 Reynold Street, City of Brunswick.
    • Total Budget: $TBD
    • Anticipated Construction Completion Date: TBD
    • Details: The project consists of the repair of the station roofs, and painting, along with pump and piping modifications. Detailed station work includes the magnetic flow meter installation, odor control unit, replacing outdated electrical and SCADA equipment, and building repairs with site improvements.
    • Purpose: The purpose of the project is to address the aging infrastructure, increase capacity to serve the area, and ensure reliable operation of these critical wastewater facilities.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2024 April Pump Station 3101, 4001, and 4002 Upgrade

2024 April Pump Station 3101, 4001, and 4002 Upgrade (2)

2024 April Pump Station 3101, 4001, and 4002 Upgrade (3)

2024 May Pump Station 3101, 4001, and 4002 Upgrade

2024 May Pump Station 3101, 4001, and 4002 Upgrade (2)

2024 May Pump Station 3101, 4001, and 4002 Upgrade (3)

2024 June Pump Station 3101, 4001, and 4002 Upgrade

2024 June Pump Station 3101, 4001, and 4002 Upgrade (2)

2024 June Pump Station 3101, 4001, and 4002 Upgrade (3)

2024 June Pump Station 3101, 4001, and 4002 Upgrade (4)

2024 July Pump Station 3101, 4001, and 4002 Upgrade

2024 July Pump Station 3101, 4001, and 4002 Upgrade 2

2024 July Pump Station 3101, 4001, and 4002 Upgrade 3

2024 August Pump Station 3101, 4001, and 4002 Upgrade

2024 August Pump Station 3101, 4001, and 4002 Upgrade (2)

2024 August Pump Station 3101, 4001, and 4002 Upgrade (3)

2024 September Pump Station 3101, 4001, and 4002 Upgrade

2024 September Pump Station 4002 Basin CIPP

2024 October Pump Station 3101, 4001, and 4002 Upgrade

2024 October Pump Station 3101, 4001, and 4002 Upgrade 2)

2024 October Pump Station 4002 Basin CIPP

2024 November Pump Station 3101, 4001, and 4002 Upgrade

2024 November Pump Station 3101, 4001, and 4002 Upgrade (2)

2024 November Pump Station 4002 Basin CIPP

2024 November Pump Station 4002 Basin CIPP (2)

2024 December Pump Station 3101, 4001, and 4002 Upgrade

2024 December Pump Station 4002 Basin CIPP

2024 December Pump Station 4002 Basin CIPP (3)

2024 December Pump Station 4002 Basin CIPP (2)

2025 January Pump Station 3101, 4001, and 4002 Upgrade

2025 January Pump Station 3101, 4001, and 4002 Upgrade (4)

2025 January Pump Station 3101, 4001, and 4002 Upgrade (3)

2025 January Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 January Pump Station 4002 Basin CIPP (3)

2025 January Pump Station 4002 Basin CIPP (2)

2025 January Pump Station 4002 Basin CIPP

2025 February Pump Station 3101, 4001, and 4002 Upgrade

2025 February Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 February Pump Station 4002 Basin CIPP

2025 March Pump Station 3101, 4001, and 4002 Upgrade

2025 March Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 March Pump Station 4002 Basin CIPP

2025 April Pump Station 3101, 4001, and 4002 Upgrade

2025 April Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 April Pump Station 3101, 4001, and 4002 Upgrade (3)

2025 April Pump Station 4002 Basin CIPP

2025 May Pump Station 3101, 4001, and 4002 Upgrade

2025 May Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 May Pump Station 3101, 4001, and 4002 Upgrade (3)

2025 May Pump Station 4002 Basin CIPP

2025 June Pump Station 3101, 4001, and 4002 Upgrade

2025 June Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 June Pump Station 3101, 4001, and 4002 Upgrade(3)

2025 July Pump Station 3101, 4001, and 4002 Upgrade

2025 July Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 August Pump Station 3101, 4001, and 4002 Upgrade

2025 August Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 August Pump Station 3101, 4001, and 4002 Upgrade (3)

2025 September Pump Station 3101, 4001, and 4002 Upgrade

2025 September Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 September Pump Station 3101, 4001, and 4002 Upgrade (3)

2025 October Pump Station 3101, 4001, and 4002 Upgrade

2025 October Pump Station 3101, 4001, and 4002 Upgrade (2)

2025 October Pump Station 3101, 4001, and 4002 Upgrade (3)

Project Info – North Mainland – North Mainland Water Loops

    • Project Number:
    • District and General Location: North Mainland District Water Loops installation along Hautala, Bailey Road, Old Jesup Road, and Golden Isles Parkway.
    • Total Budget: $2.M
    • Anticipated Construction Completion Date: Summer 2023
    • Details: The project consists of water loop installations along Hautala, Bailey Road, Old Jesup Road, and Golden Isles Parkway in the North Mainland District via open-cut and trenchless methods.
    • Purpose: The purpose of the project is to eliminate dead ends where water can become stagnant from lack of use, and improve water quality, and fire protection for JWSC customers.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2023 NOVEMBER NORTH MAINLAND WATER LOOPS

2023 DECEMBER NORTH MAINLAND WATER LOOPS (1)

2023 DECEMBER NORTH MAINLAND WATER LOOPS (2)

2024 JANUARY NORTH MAINLAND WATER LOOPS

2024 JANUARY NORTH MAINLAND WATER LOOPS(2)

2024 FEBRUARY NORTH MAINLAND WATER LOOPS

2024 FEBRUARY NORTH MAINLAND WATER LOOPS (2)

2024 APRIL NORTH MAINLAND WATER LOOPS

Project Info – North Mainland – Canal Road Water Production Facility

    • Project Number:
    • District and General Location: North Mainland District Canal Road Well Site at104 Canal Road
    • Total Budget: $TBD
    • Anticipated Construction Completion Date: Summer 2023
    • Details: The project consists of the conversion of an existing fire well to a Water Production Facility on Canal Road in the North Mainland District.
    • Purpose: The purpose of the project is to meet supply-demand and capacity, water storage capacity, and increased fire flow capacity into the region.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2024_April_Canal_Road_Water_Production_Facility

2024_May_Canal_Road_Water_Production_Facility

2024_June_Canal_Road_Water_Production_Facility (2)

2024_June_Canal_Road_Water_Production_Facility

2024_July_Canal_Road_Water_Production_Facility

2024_July_Canal_Road_Water_Production_Facility (2)

2024_August_Canal_Road_Water_Production_Facility

2024_September_Canal_Road_Water_Production_Facility

2024_September_Canal_Road_Water_Production_Facility (2)

2024_October_Canal_Road_Water_Production_Facility

2024_October_Canal_Road_Water_Production_Facility (2)

2024_October_Canal_Road_Water_Production_Facility (3)

2024_November_Canal_Road_Water_Production_Facility (2)

2024_November_Canal_Road_Water_Production_Facility

2024_December_Canal_Road_Water_Production_Facility

2024_December_Canal_Road_Water_Production_Facility (3)

2024_December_Canal_Road_Water_Production_Facility (2)

2025_January_Canal_Road_Water_Production_Facility

2025_January_Canal_Road_Water_Production_Facility (2)

2025_February_Canal_Road_Water_Production_Facility

2025_March_Canal_Road_Water_Production_Facility

2025_April_Canal_Road_Water_Production_Facility

2025_May_Canal_Road_Water_Production_Facility

2025_June_Canal_Road_Water_Production_Facility

2025_July_Canal_Road_Water_Production_Facility

2025_August_Canal_Road_Water_Production_Facility

2025_October_Canal_Road_Water_Production_Facility

2025_November_Canal_Road_Water_Production_Facility

2025_December_Canal_Road_Water_Production_Facility

2026_January_Canal_Road_Water_Production_Facility

2026_February_Canal_Road_Water_Production_Facility

Project Info – North Mainland – Community Road Sewer Expansion

    • Project Number:
    • District and General Location: North Mainland District in the Community Road Business Area
    • Total Budget: $TBD
    • Anticipated Construction Completion Date: Summer 2023
    • Details: The project consists of 12-inch Water and 12-inch Sewer Extension rehabilitation along the Community Road Business Area in the North Mainland District.
    • Purpose: The purpose of the project is to provide the capacity to serve and extend critical infrastructure with new service lines. This will reduce the operation and maintenance costs borne by the customer and promote larger business development in the area.
    • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

    Visual Summary:

Monthly Active Construction Project Photo Report(s):

2025 August North Mainland – Community Road Sewer Expansion

2025 October North Mainland – Community Road Sewer Expansion

2025 November North Mainland – Community Road Sewer Expansion

2025 December North Mainland – Community Road Sewer Expansion

2026 January North Mainland – Community Road Sewer Expansion

2026 February North Mainland – Community Road Sewer Expansion

2026 March North Mainland – Community Road Sewer Expansion

Project Info – North Mainland – Arco Water & Sewer Extension

  • Project Number: #2016
  • District and General Location: North Mainland District in the Arco Area Neighborhood
  • Total Budget: $4.1M
  • Anticipated Construction Completion Date: Winter 2022
  • Details: The project consists of 8-inch Water and 8 to 10-inch Sewer Extension rehabilitation along the Acro Area Neighborhood in the North Mainland District.
  • Purpose: The purpose of the project is to provide capacity to serve, extend critical infrastructure with new service lines, and enhance fire protection.
  • Have More Questions? Please Contact W. Todd Kline, P.E., Director of Engineering by email here: tkline@bgjwsc.org

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2022_May_Arco_Area_Water_And_Sewer_Extension

2022_June_Arco_Area_Water_And_Sewer_Extension

2022_July_Arco_Area_Water_And_Sewer_Extension

2022_August_Arco_Area_Water_And_Sewer_Extension

2022_September_Arco_Area_Water_And_Sewer_Extension

2022_October_Arco_Area_Water_And_Sewer_Extension

2022_November_Arco_Area_Water_And_Sewer_Extension

2022_December_Arco_Area_Water_And_Sewer_Extension

2023_January_Arco_Area_Water_And_Sewer_Extension

2023_February_Arco_Area_Water_And_Sewer_Extension

2023_March_Arco_Area_Water_And_Sewer_Extension

2023_April_Arco_Area_Water_And_Sewer_Extension

2023_May_Arco_Area_Water_And_Sewer_Extension

2023_June_Arco_Area_Water_And_Sewer_Extension

2023_July_Arco_Area_Water_And_Sewer_Extension

2023_August_Arco_Area_Water_And_Sewer_Extension

2023_September_Arco_Area_Water_And_Sewer_Extension

2023_October_Arco_Area_Water_And_Sewer_Extension

2023_November_Arco_Area_Water_And_Sewer_Extension

2023_December_Arco_Area_Water_And_Sewer_Extension

2024_January_Arco_Area_Water_And_Sewer_Extension

2024_February_Arco_Area_Water_And_Sewer_Extension

2024_April_Arco_Area_Water_And_Sewer_Extension

2024_May_Arco_Area_Water_And_Sewer_Extension

2024_June_Arco_Area_Water_And_Sewer_Extension

2024_July_Arco_Area_Water_And_Sewer_Extension

2024_August_Arco_Area_Water_And_Sewer_Extension

2024_September_Arco_Area_Water_And_Sewer_Extension

2024_October_Arco_Area_Water_And_Sewer_Extension

2024_November_Arco_Area_Water_And_Sewer_Extension

2024_November_Arco_Area_Water_And_Sewer_Extension (2)

2024_December_Arco_Area_Water_And_Sewer_Extension

2024_December_Arco_Area_Water_And_Sewer_Extension (2)

2025_January_Arco_Area_Water_And_Sewer_Extension

2025_January_Arco_Area_Water_And_Sewer_Extension (2)

2025_February_Arco_Area_Water_And_Sewer_Extension

2025_March_Arco_Area_Water_And_Sewer_Extension

2025_April_Arco_Area_Water_And_Sewer_Extension

Project Info – Pump Station 2002 Forcemain Replacement

  • Project Number: #2014
  • District and General Location: Saint Simons Island District along Arnold Road
  • Total Budget: $TBD
  • Anticipated Construction Completion Date: TBD
  • Details: The project consists of 12-inch forcemain rehabilitation along Arnold Road in the Saint Simons Island District.
  • Purpose: The purpose of the project is to prioritize pipe repairs, rehabilitation, and replacements based on a risk-based, asset management strategy balancing the probability of a pipe failure versus the consequence of a failure to the service area (i.e., size of community impact). Those areas with the greatest need where repairs would have the greatest impact are where JWSC focuses our efforts
  • Have More Questions? Please Contact Andrew Burroughs, P.E., Executive Director, by email here: aburroughs@bgjwsc.org

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2022_November_PS_2002_FORCEMAIN_REPLACEMENT

2022_December_PS_2002_FORCEMAIN_REPLACEMENT

2023_January_PS_2002_FORCEMAIN_REPLACEMENT

2023_February_PS_2002_FORCEMAIN_REPLACEMENT

2023_March_PS_2002_FORCEMAIN_REPLACEMENT

2023_April_PS_2002_FORCEMAIN_REPLACEMENT

2023_May_PS_2002_FORCEMAIN_REPLACEMENT

2023_June_PS_2002_FORCEMAIN_REPLACEMENT

Project Info – Mainland – Water Pollution Rehab-Academy

  • Project Number: #906
  • District and General Location: Academy Creek Water Pollution Control Plant on 2909 Newcastle Street.
  • Total Budget: $7.2M
  • Anticipated Construction Completion Date: Summer 2022
  • Details: The project has a variety of system improvement projects related to rehabilitation or replacement of unit processes and facilities at the plant to ensure continuous and reliable operations.
  • Purpose: The purpose of the project is to more effectively treat current flows and treat the estimated future flows, ensure long-term functionality, and Federal and State permit compliance.
  • Have More Questions? Please contact Andrew Burroughs, P.E., Executive Director – aburroughs@bgjwsc.org

Visual Summary:

Monthly Active Construction Project Photo Report(s):

2022_April_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_May_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_June_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_July_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_August_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_September_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_October_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_November_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2022_December_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2023_January_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2023_February_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF

2023_March_Project_Photos_-_Mainland_Water-Pollution-Control-Rehab-Academy-Creek-WPCF